ADA BRIDGE - BELGRADE

print
email
Last update by Mitar Papovic

INVESTOR: Directorate of Land and Construction of Belgrade
MAIN CONTRACTOR: Ogranak Porr Bau GmbH, Belgrade
YEAR BUILT: 2012-2014.

 

During the project on the southern access roads to the Ada Bridge in Belgrade, our company carried out various works as a subcontractor for the General contractor Ogranak Porr Bau GmbH, Belgrade.
Our project team consisted of about 100 professional craftsmen (carpenters, concrete workers ...) who performed work on 3 viaduct - bridges - Radnicka North and South, BGM, with a total length of about 900m¹ and also earthworks, drainage works, installation of  precast elements -fascia and NJ Barriers, installation of pedestrian fences, paving, making footpaths ..

 

The scope of the work that we have done is divided into four distinct segments:

I – Radnicka Street viaduct – North and South (2 x 313,00 meters) and BGM (Belgrade Metro) viaduct (1 x 290,00 meters).  In this phase of the project we executed all the works except piling, which includes the construction of pile caps, abutment and retaining walls, piers and superstructures. The work was performed in the period from March of 2012 to June of 2013 and completed in time. As a part of this contract we constructed one small 35 meters long bridge over the Topcider river, constructed on abutment walls, with I beams and a 20 centimeter thick deck slab over the I beams.

 

II – South approach roads – Auxilary works. In this phase of the project we executed all the Auxilary works except for waterproofing for all approach ramps (8 viaducts). These works included installation of fascia edge beams, precast New Jersey barriers, pedestrian footpaths and steel pedestrian handrails. The work was performed in the period from June of 2012 to December of 2013 and completed in time. All the materials and equipment used and installed were supplied by our company.  

 

IIISouth approach roads – Earthworks and asphalt works. In this phase of the project we executed all the earth and paving works for all approach ramps (8 viaducts). These works included replacement of soil, excavations, backfilling, sub-base layers, kerbs and asphalt works. The work was performed in the period from June of 2012 to December of 2013 and completed in time. All the materials and equipment used and installed were supplied by our company.  

 

IV – South approach roads Ada Bridge – Drainage works. In this phase of the project we executed all the drainage  works on the project. These works included installation excavation, installation of the pipes, precast shafts, manholes and gullies. The work was performed in the period from September of 2012 to December of 2013 and completed in time. All the materials and equipment used and installed were supplied by our company.